HPP BOSKOV MOST

HPP BOSKOV MOST

HPP BOSKOV MOST

HPP BOSKOV MOST

Design and Construction of a 70 MW Hydropower plant

Dam (RCC 33m high, 250m wide), 10km headrace tunnel, 6 Intakes with 3 siphons and 20km channels, Penstock (head 357m), Powerhouse (Francis and vertical Generator), 110KV Switchyard

JSC ELEM (Macedonian Power Plants).

Address of Client: 11 Oktomvri 9, Skopje 1000, North Macedonia

 

Main scope of services:

  • Preparation of design and procurement of hydromechanical parts (Valves and Penstock);
  • Preparation of design and procurement of 110 KV switchyard and power line to the grid (33km);
  • Preparation of ESIA monitoring Plan and
  • Provision of support during project implementation and post-completion.
Category:
Date:
Colenco.net
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.