DEVELOPMENT OF THE ENERGY SECTOR VII – IMPROVEMENT OF TRANSMISSION NETWORK

DEVELOPMENT OF THE ENERGY SECTOR VII – IMPROVEMENT OF TRANSMISSION NETWORK

DEVELOPMENT OF THE ENERGY SECTOR VII – IMPROVEMENT OF TRANSMISSION NETWORK

NORTH MACEDONIA: DEVELOPING ENERGY TRADING AND PROJECT MANAGEMENT SKILLS FOR ESM

The Project concerns the rehabilitation and modernization of parts of the 110kV and 220kV transmission network of KOSTT. As part of this development effort, the following Project measures are foreseen, separated in 7 Lots:

  • LOT 1: Construction of a new Substation
    • Construction of the new SS 110/35/10(20) kV Dragash with 1×40 MVA power transformer
    • Installation of a variable shunt reactor (VSR) 400 kV / 100 MVAr in substation Ferizaj 2;
  • LOT 2: Supply and installation of equipment to adopt Local SCADA (RTU & SCS);
  • LOT 3: Replacement of existing SCADA/EMS system for KCS and EKCS;
  • LOT 4: Migration to advanced telecommunication systems with IP-MPLS;
  • LOT 5: Design, Supply, and Installation of power transformers (WBIF Option)
  • LOT 6: Transmission Lines and Underground Cables (Partially WBIF Option)
  • LOT 7: Revitalisation and Reinforcement of 110kV Line Segments (IPA Option)

Project financed by KfW.

 

Main scope of services:

  • Task 1: Preliminary Design and Tender Documents
    • Concept Review and Preparation of Preliminary Design
      • Data collection
      • Preparation of Inception report
      • Preparation of Project Planning Report
      • Execution of ESHS Related activities
    • Preparation of PQ and Tender Documents
  • Task 2: Assistance during Tendering
    • Assistance during evaluation of PQ applications
    • Preparation of PQ Evaluation Report
    • Assistance during Tender Process
    • Assistance during Bid Evaluation Process, Contract negotiations and Award
    • Preparation of Tender Evaluation report
  • Task 3: Supervision of Design Works, Construction Works and Supplies
    • Contract supervision
      • Site Inspection meetings
      • Review, verify and approve Contractor’s Design
      • Permanent On-Site Supervision
      • Participate in FAT
    • Commissioning
  • Task 4: Services during Contractor’s DNP and Closure of Project
    • Defect Notification Period Management

 

Date:
Colenco.net
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.