TECHNICAL DUE DILIGENCE FOR 4 SMALL HYDRO POWER PLANT PROJECT:

TECHNICAL DUE DILIGENCE FOR 4 SMALL HYDRO POWER PLANT PROJECT:

TECHNICAL DUE DILIGENCE FOR 4 SMALL HYDRO POWER PLANT PROJECT:

TECHNICAL DUE DILIGENCE FOR 4 SMALL HYDRO POWER PLANT PROJECT:

  • SHPP Pena 82 16.8MW
  • SHPP Pena 84 28.9MW
  • SHPP Pena 85 24.65MW
  • SHPP Sheliche 91 15.73MW.

The purpose of this assignment is to inform the Borrower about the suitability and sustainability of the projects’ designs as well as the potential risks and improvements of the planned small hydro power plants.

Gravis Hydro, Macedonia

 

Main scope of services:

  • Preparation of Technical Due Diligence:
    • Summary of the review of all technical reports;
    • Provision of other relevant information about the suitability and sustainability of the project’s design;
    • Justification of the viability of the project.
Category:
Date:
Colenco.net
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.