TECHNICAL DUE DILIGENCE FOR 4 SMALL HYDRO POWER PLANT PROJECT:
TECHNICAL DUE DILIGENCE FOR 4 SMALL HYDRO POWER PLANT PROJECT:
- SHPP Pena 82 16.8MW
- SHPP Pena 84 28.9MW
- SHPP Pena 85 24.65MW
- SHPP Sheliche 91 15.73MW.
The purpose of this assignment is to inform the Borrower about the suitability and sustainability of the projects’ designs as well as the potential risks and improvements of the planned small hydro power plants.
Gravis Hydro, Macedonia
Main scope of services:
- Preparation of Technical Due Diligence:
- Summary of the review of all technical reports;
- Provision of other relevant information about the suitability and sustainability of the project’s design;
- Justification of the viability of the project.
Category:
Date:
June 4, 2025